Concrete Slab Jacking

Funding

Budget Expenditures
Encumbrances Budget Remaining
Fiscal Year 14-15
$30,000
$30,357
$1,039

Total
$30,000
$30,347
$1,039
($1,386)
NOTE: This project does not roll forward each year. A new amount is budgeted each year.

Project Description
This project includes slab jacking at locations where settling has occurred on roadway slab sections at locations throughout the City.

Future Operating Impact
This is an annual replacement/maintenance program, so there is no impact on future operational costs.

First Quarter FY 14-15
Project is 90% completed.

Second Quarter FY 14-15
Project is completed.